Changing the Period for the SAP Overview Page

FlexNet Manager Suite 2021 R1 (On-Premises)

To change the period covered by the Named User Licenses or License Utilization graph on the SAP Overview page:

  1. Click Change period in the lower-right corner of the item.
    The dialog Change gadget-type Period displays.
  2. In the Interval field, select the interval groupings to include in the graph (monthly, quarterly, or yearly).
  3. In the Duration field, select the number of intervals to include in the graph. For example, if you selected an interval of Quarterly, and a duration of 4, then the graph will cover all four quarters of a year.
  4. After setting these two fields, the format of the End Date field changes according to the interval you have selected. Complete this field (and any additional fields that display) as described below.
    • Monthly

      Select the Use the current month check box if you want to use the current month as the end date.

      Otherwise, clear the check box. Month and Year fields are displayed to enable you to specify the month in which the data should end.

    • Quarterly

      Month and Year fields are displayed to enable you to specify the month in which the data should end. If, for example, you selected to end a graph on March 2019, the first quarter of data shown in the graph would cover the period January-March, 2019.

    • Yearly

      Month and Year fields are displayed to enable you to specify the month in which the data should end. If, for example, you selected to end a graph on March 2019, the first year of data shown in the graph would cover the period April 2018 to March 2019.

  5. Click Apply to confirm the change in period.

The dialog closes, and the graphic summary is refreshed to cover the new period.