Setting Up a Weekly Normalize Schedule
Data Platform
Set up a weekly normalize schedule:
|
1.
|
Click the Details icon to open the Schedule panel. |
|
2.
|
Select the Advanced Schedule radio button. The Advanced Schedule dialog opens. |
Advanced Schedule dialog

|
3.
|
Click the Start Date field to choose a date from the calendar. |
|
4.
|
Click the Start Time field to choose a time from the time list. |
|
5.
|
Enter a number in the Recur Every entry field. Values are 1-4. |
|
6.
|
Select Weeks from the dropdown list. |
|
7.
|
Select checkboxes for each day in the week that you want to run Normalize. |
For example, to run Normalize every Monday and Thursday, enter 1 in the Recur Every entry field and place checks in the Monday and Thursday checkboxes.
|
8.
|
Click OK. The Advanced schedule status is displayed in the Details panel. Click the Edit icon to modify the schedule settings. |