Scheduling Classic Reports

Using the Report Scheduling page, you can schedule a report to run at the same time on specified days. This way, you can schedule a report to run nightly, weekly, monthly, and so on.

Note:Only a user with the Super Administrator role or the user who originally started running the report can cancel a report while it is in progress, whether the report is run manually or by the FlexNet Manager for Engineering Applications scheduler.

To run a report at scheduled times:

1. From the Reporting tab, under Classic Reporting, click Report Configurations. This displays the Report Configurations page.
2. Click the Schedule button to the right of the report configuration for which you want to schedule a run. This opens the Report Scheduling page.
3. In the Run Report section, click one of the radio buttons:
Not Scheduled—This report is not scheduled to run.
These days at (hh:mm)—Specify a time (using a 24-hour clock) and select the days of the week on which you want the report to run.
These months on day (number of day in a month) at (hh:mm)—Select the day, specify a time (using a 24-hour clock), and select the months on which you want the report to run.
4. Click Save.

After the report runs, the report output is available in the Report Inbox.

See Also